Circular No.: 19-177 - NEW FIT-OUT SCHEDULE OF ELEVATOR REFURBISHMENT
Circular No.: 19-177
Date : 4 October 2019
To : ALL SAN LORENZO TOWER RESIDENTS
Subject : NEW FIT-OUT SCHEDULE OF ELEVATOR REFURBISHMENT
Dear Unit Owners and Residents,
In reference with the Circular No.19-118 Elevator Refurbishment, please be informed that EJ Metals – nominated contractor will be needing to extend the works due to some uncontrollable factors.
New schedule will be as follows:
ELEVATOR |
WORK TIME LINE |
Passenger Elevator (PE) 1 |
July 24 – Oct. 8, 2019 |
Passenger Elevator (PE) 2 |
Oct. 8 – Nov. 5, 2019 |
Passenger Elevator (PE) 3 |
Nov. 5 – Nov. 26, 2019 |