Circular No.: 19-186 - SCHEDULE OF ELEVATOR REPAIR
Circular No.: 19-186
Date : 26 October 2019
To : LAGUNA UNIT OWNERS RESIDENTS
Subject : SCHEDULE OF ELEVATOR REPAIR
As part of our building maintenance effort to ensure reliability and efficiency of all four (4) elevators, KONE will do minor repair works at Laguna elevators.
The following is schedule of work and expected shutdown of each of the elevator as provided by KONE:
Passenger Elevator 1
|
|
Passenger Elevator 2
|
28-Oct-19
|
8am to 5pm
|
|
5-Nov-19
|
8am to 5pm
|
29-Oct-19
|
8am to 5pm
|
|
6-Nov-19
|
8am to 5pm
|
30-Oct-19
|
8am to 3pm
|
|
7-Nov-19
|
8am to 5pm
|
31-Oct-19
|
8am to 5pm
|
|
8-Nov-19
|
8am to 12nn
|
4-Nov-19
|
8am to 12nn
|
|
|
|
|
|
|
|
|
Passenger Elevator 3
|
|
Service Elevator
|
30-Oct-19
|
3pm to 5pm
|
|
9-Nov-19
|
3pm to 5pm
|
4-Nov-19
|
1pm to 5pm
|
|
13-Nov-19
|
1pm to 5pm
|
8-Nov-19
|
1pm to 5pm
|
|
14-Nov-19
|
8am to 5pm
|
9-Nov-19
|
8am to 3pm
|
|
15-Nov-19
|
8am to 5pm
|
11-Nov-19
|
8am to 5pm
|
|
16-Nov-19
|
8am to 5pm
|
12-Nov-19
|
8am to 5pm
|
|
18-Nov-19
|
8am to 5pm
|
13-Nov-19
|
8am to 12nn
|
|
|
|
We sincerely apologize to the inconvenience you will be experiencing on the above-mentioned days but rest assured we are doing our best to keep all our facilities in top operational condition.
Thank you and we hope for your usual cooperation on this matter.
For and on behalf of The Residences at Greenbelt Condominium Corporation